Discover the latest progress report on the sixth phase of the renovation project with this H5 presentation crafted by Eqxiu, the leading online design platform. This comprehensive report details the progress at 80% completion for the masonry and杂工泥水 (tile and stone) work, along with the nearly finished ceiling construction and 70% completion of lighting installation. The first coat of paint for the decorative surface is also completed. Further, the report highlights the installation status of various components, including 70% completion for the bathroom and entrance cabinets, 80% for kitchen cabinets, and 80% for interior door frames and doors. However, the installation of wooden flooring and bathroom fixtures has not yet commenced. This Eqxiu-powered H5 design allows for quick and easy creation, leveraging Eqxiu's extensive template library.
六期精装进度